Financial Details
Information Required by the Bond Transparency Act of 2017
Evidence of Indebtedness Form
Date of Posting: December 17, 2019
Name of School District: ISD #22 Canadian County, OK (Piedmont Public Schools)
Address: 713 Piedmont Road North
Piedmont, OK 73078
Date of New Bond Election: February 11, 2020
Amount of New Bond Election: $35,735,000
Projects to be completed with New Bond Election Proceeds:
Proposition:
Construct, equip and furnish Phase I of
the new Athletic Center to include but not be
limited to: site preparation, foundation, foundation
steel $3,265,000.00
Construct, equip and furnish Phase II of
the new Athletic Center to include but not be
limited to: complete the foundation and
exterior partitions $1,945,000.00
Construct, equip and furnish Phase III of
the new Athletic Center to include but not be
limited to: completion of the exterior partitions,
roof and additional roofing fixtures and equipment $2,220,000.00
Construct, equip and furnish Phase IV of
the new Athletic Center to include but not be
limited to: interior partitions, doors, windows and
concessions $2,455,000.00
Construct, equip and furnish Phase V of
the new Athletic Center to include but not be
limited to: completion of the interior
partitions to include offices and locker rooms $2,865,000.00
Construct, equip and furnish Phase VI of
the new Athletic Center to include but not be
limited to: completion of the new gym and flooring
$2,985,000.00
Construct, equip and furnish Completion Phase of
the new Athletic Center to include but not be
limited to: addition school furniture, fixtures and
equipment to include goals and bleachers $3,240,000.00
Construct, equip and furnish Phase I of
the new Middle School Addition to include but not be
limited to: partial demolition, site preparation and
foundation and exterior partitions $3,610,000.00
Construct, equip and furnish Phase II of
the new Middle School Addition to include but not be
limited to: completion of the exterior partitions, roof
and roofing fixtures, HVAC and addition HVAC
equipment $4,630,000.00
Construct, equip and furnish Completion Phase of
the new Middle School Addition to include but not be
limited to: completion of the interior partitions,
construct and furnishing the cafeteria; construct and
furnishing a gym/saferoom, band room, additional
classrooms and additional school district
furniture, fixtures and equipment $8,320,000.00
Acquire band equipment $ 200,000.00
Total: $35,735,000.00
Unpaid/Unfinished Bonds Previously Approved by voters of the District:
- Bond Election date: April 3, 2007
- Amount of original election: Proposition No. 1: $13,925,000
- Amount of bonds outstanding from this election(s):$1,630,000 left to be paid off
- Description of use of bond proceeds:
Proposition No. 1:
Construct, equip and furnish Completion Phase of a new
Elementary school facility to include but not be limited
To carpeting and flooring, classroom and office furniture,
Fixtures and equipment $1,630,000
- Bond Election date: December 14, 2010
- Amount of original election: Proposition: $19,450,000
- Amount of bonds outstanding from this election(s):$8,445,000 left to be paid off
- Description of use of bond proceeds:
Proposition
Construct, equip and furnish the Completion Phase of a new
5th and 6th Grade Classroom Center; new gymnasium and new
Cafeteria, to include but not be limited to interior partitions,
Lighting equipment and fixtures, plumbing equipment and
Plumbing fixtures, flooring, gymnasium floor, bleachers and
Other gym equipment; cafeteria equipment, stage lighting
And sound system and additional school furniture, fixtures and
Equipment $8,445,000
- Bond Election date: August 23, 2016
- Amount of original election: Proposition No. 1: $70,690,000
Proposition No. 2: $1,000,000
- Amount of bonds outstanding from this election(s):$71,690,000 left to be paid off
- Description of use of bond proceeds:
- Amount of original election: Proposition No. 1: $70,690,000
Proposition No. 1:
Construct, equip and furnish a High School Addition
and Renovation at the High School to include
but not be limited to: Classrooms, Offices, Restrooms,
flooring and wall improvements, foundation,
and site improvements $28,011,962.00
Construct, equip and furnish a new Early Childhood
Center to include but not be limited to: Classrooms,
restrooms, offices and additional furniture, fixtures
and equipment $21,895,681.00
Construct, equip and furnish a Northwood Storm
Shelter/Classroom Addition to include but not be limited
to science labs, media center $ 3,380,456.00
Construct, equip and furnish Piedmont Elementary
Gym/Shelter/Commons area and cafeteria, stage and
concessions $ 6,066,041.00
Construct, equip and furnish a new Indoor Facility to include
but not be limited to locker rooms, batting cages, offices
and a weight room $ 2,449,501.00
Acquire and install new turf at the Track and football field $ 2,779,486.00
Construct, equip and furnish new Baseball/Softball fields $ 5,806,873.00
Acquire and install new HVAC units and acquire band uniforms $ 300,000.00
Total: $70,690,000.00
Proposition No. 2:
Acquire student transportation equipment $1,000,000.00
If real property is included, provide street address:
High School improvements located at: 1055 Edmond Road NW, Piedmont, OK 73037
Early Childhood Center located at: 11020 W. Memorial Road, Yukon, OK 73099
Northwood School located at: 14100 Northwood Drive, Yukon, OK 73099
Piedmont Elementary located at: 1011 Piedmont Road North, Piedmont, OK 73078
Football field and Track located at: 808 2nd Street, Piedmont, OK 73078
Locker Room/Weight Room/Office facility located at: 808 2nd Street, Piedmont, OK 73078
5th and 6th Grade Center located at: 977 Washington Ave., Piedmont, OK 73078
Stone Ridge Elementary improvements located at: 10000 W. Memorial Rd., Yukon, OK 73099